MRT Corp today revealed that the incident which claimed three lives at a constru…

MRT Corp today revealed that the incident which claimed three lives at a construction site was due to lack of supervision at the site.

Findings of the investigation conducted on the incident found that the 350-tonne viaduct deck span had toppled because of poor sub-contractor management, among other factors.

More to follow: http://www.malaysiakini.com/news/275112